Team Charter for Experimental Ensemble Forecast System (XEFS)
Design and Gap Analysis
Objective: Carry out:
- Design of the Experimental Ensemble Forecast System (XEFS),
- Gap analysis of existing data, science, techniques, tools, and software, and
- Planning of development and implementation achievable within 2 years.
As the baseline prototype system, XEFS should:
- Operationally serve the RFCs as an interim ensemble forecasting capability,
- Provide an ensemble forecasting infrastructure common to both OHD and RFCs to develop
requirements and operations concepts, identify areas of need and potential science enhancements,
and assess value and performance of additional capabilities and features, and
- Expedite maturation of system components that can be readily transitioned to operations within
2 years of implementation of the Service Oriented Architecture.
While XEFS is not expected to comprise all major functionalities desirable in a hydrologic ensemble
forecast system in order to fast-track development and implementation, it should be extensible to
allow data assimilation, distributed modeling and other capabilities as future enhancements. For
flexibility and transparency necessary for efficient joint development by OHD and RFCs, XEFS should
be open and modular. While the primary thrust of XEFS is on providing ensemble forecasting capability
for daily short-term (Day 1~14) forecasting operations at the RFCs using lumped models, as an
integrated ensemble forecast system XEFS should also be able to support seamlessly long-term (~1yr)
ensemble forecasting and appropriately leverage climate forecast information. The gap analysis
should include identification and assessment of existing capabilities, identification of the needs
to realize XEFS, identification and prioritization of the gaps, assessment of current resources
available for gap-closing, and approximate cost of additional gap-closing measures.
The team will:
- Design XEFS, based on the short-term ensemble CONOPS developed jointly by DSST and OHD, and
expert knowledge and opinions of the team members,
- Carry out gap analysis for development and implementation of XEFS,
- Recommend specific gap-closing measures, and
- Develop project plan for XEFS development and implementation achievable within 2 years.
It is understood that the process of developing the XEFS will be evolutionary and that the
project plan must have the flexibility to identify new requirements and shift emphasis and workload
as deemed appropriate.
Scope and Authority:
- Recommendations must be readily actionable by OHD and the participating RFCs, leading to
formation of the joint development team and kick-off of its activities immediately following
this team's activities.
- Analysis must be objective.
- Basis for decisions will be decided on by the team.
- Staff time is expected to be approximately 1 day per week.
- Travel expenses, if needed, may be covered by a combination of OHD and the team member's
organization.
Termination Date: The team will be formed and commence activities in late Dec 2006 and
remain in place for a period of up to 3 months.
Success Criteria: An agreed-to design and development plan for XEFS that provides a clear
pathway for the implementation within 2 years.
Membership: The team will be made of the following individuals. The team mentor will be
Gary Carter. Additional personnel from the RFCs, NWS Regions or Headquarters may participate as
consultants.
Team Members
Robert Hartman |
CNRFC |
Team Co-Leader |
Dong-Jun Seo |
OHD/HSMB |
Team Co-Leader |
Bill Lawrence |
ABRFC |
Team Member |
Steve Shumate |
CBRFC |
Team Member |
Joe Ostrowski |
MARFC |
Team Member |
John Halquist |
NCRFC |
Team Member |
Chris Dietz |
OHD/HSEB |
Team Member |
Mary Mullusky |
OCWWS/HSD |
Team Member |
|